Architect's Guide: Agile Scope Management & Fee Protection Protocol
Contract Baseline & Exclusions
Defining the rigid perimeter of the base contract before design begins
- Define specific number of design iteration rounds (e.g., 3 per phase)
- Explicitly list 'Excluded Services' (e.g., 3D renderings, interior styling)
- Establish a clear 'Stop Work' threshold for non-payment events
- Set 'Decision Deadlines' clause for client feedback turnover
- Include a 'Material Volatility' clause for 2026 supply chain pricing
- Define exact deliverable formats (PDF vs. CAD/BIM ownership)
- Specify the exact number of in-person site visits included
Client Communication Governance
Structured channels to prevent text-message creep and informal instruction
- Designate one primary 'Decision Maker' if client is a couple/group
- Establish a single channel for official instructions (e.g., project portal, not WhatsApp)
- Set 'Blackout Hours' expectation (no responses weekends/after 6 PM)
- Implement a weekly 'Status Email' template to bundle small questions
- Create a 'Parking Lot' document for out-of-scope wishlist items
- Require written confirmation for any verbal site instruction within 24 hours
Design Iteration Control
Managing the Schematic Design (SD) and Design Development (DD) flux
- Present strictly two (2) distinct initial concept options
- Require signature sign-off on SD floor plans before DD elevation work
- Track 'Option Creep' visually showing design evolution vs. budget
- Limit finish material selection rounds to two sets of samples
- Mandate 'Cost Check' estimates at end of SD and DD phases
- Freeze all structural grid changes prior to Construction Documents (CD)
Change Order Defense Mechanisms
Systems to identify, quantify, and charge for late-stage changes
- Utilize a 'Potential Change Order' (PCO) log visible to the client
- Attach fee values to time delays caused by client indecision
- Require 'Change Directives' to be signed before drafting work begins
- Flag 'late-breaking' appliance changes that impact cabinetry dimensions
- Isolate electrical/RCP changes requested after permit submission
- Maintain a separate folder for 'Owner-Requested Changes' vs. 'Field Conditions'
Construction Admin (CA) Boundaries
Keeping the architect's role strictly to observation, not supervision
- Clarify 'Means and Methods' are strictly the Contractor's liability
- Limit RFI response times to standard business days (48-72 hours)
- Reject incomplete product submittals without review ('Return Not Reviewed')
- Document site observations with photos linked to plan markers instantly
- Require Contractor to propose solutions in RFIs, not just ask questions
- Enforce the distinction between 'Site Visit' and 'On-Site Meeting'
Closeout & Retainer Operations
Finalizing the project file and ensuring final profitability
- withholding of final deliverables until final invoice clearance
- Secure 'Certificate of Substantial Completion' prior to owner move-in
- Execute a formal 'Handover Walkthrough' distinct from punch-list generation
- Archive BIM models and DWG files in 'Read-Only' formats
- Issue final lien waivers only upon confirmed receipt of funds
- Request professional photography scheduling within 30 days of completion
- Debrief internal team on 'Profit Leaks' for this specific project
Frequently Asked Questions
How do I bill for 'quick' text messages from clients?
Do not bill individually. Instead, log them as 15-minute increments in your time-tracking software and aggregate them into a 'Communication/Administration' line item on your monthly invoice.
What is the best way to stop scope creep during Design Development?
Implement 'Hard Freeze' milestones. Require a physical signature on the floor plan and exterior elevations before beginning any interior detailing or electrical layouts.
Can I charge for rework if the client changes their mind after sign-off?
Yes, and you must. Reference the specific 'Sign-Off Date' in your contract and issue an Additional Service Request (ASR) before starting the rework drawings to establish professional boundaries.